The Park at Spanish Ridge

Description

On this project, Sunland crack-filled, seal-coated, and re-striped up to 415,360 square feet. Sunland applied 2 coats, which was around 11,540 gallons of Polymer Modified MasterSeal (PMM). This project was scheduled for production over several consecutive weekends to minimize disruption of all businesses on site.

Owner

The Park at Spanish Ridge

Location

Las Vegas, NV